Davis-Bacon
TX20260232 (Rev 1)
Coverage: Texas • Bowie.
Published: May 18, 2026
Status: Active
Standard: Yes
Occupation Rates
Parsed from SAM WD content. Always validate final applicability and source text before pricing decisions.
| Occupation | Base | Fringe |
|---|---|---|
| BOILERMAKER | $33.17 | $24.92 |
| ELECTRICIAN | $30.05 | $12.01 |
| POWER EQUIPMENT OPERATOR ((3) HYDRAULIC CRANES 59 TONS AND UNDER) | $32.35 | $13.10 |
| POWER EQUIPMENT OPERATOR ((1) TOWER CRANE) | $32.85 | $13.10 |
| IRONWORKER: ORNAMENTAL | $28.26 | $8.13 |
| PIPEFITTER | $39.76 | $14.04 |
| TRUCK DRIVER: WATER TRUCK | $12.00 | $4.11 |
| TRUCK DRIVER: SEMI-TRAILER TRUCK | $12.50 | $0.00 |
| TRUCK DRIVER: FLATBED TRUCK | $19.65 | $8.57 |
| TRUCK DRIVER: DUMP TRUCK | $12.39 | $1.18 |
| TILE SETTER | $14.74 | $0.00 |
| TILE FINISHER | $11.22 | $0.00 |
| SHEET METAL WORKER (HVAC DUCT INSTALLATION ONLY) | $22.73 | $7.52 |
| ROOFER | $13.75 | $0.00 |
| PLUMBER | $21.35 | $4.55 |
| PAINTER: BRUSH, ROLLER, AND SPRAY | $14.45 | $0.00 |
| OPERATOR: ROLLER | $12.70 | $0.00 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $16.03 | $0.00 |
| OPERATOR: MECHANIC | $17.52 | $3.33 |
| OPERATOR: LOADER | $12.62 | $2.42 |
| OPERATOR: GRADER/BLADE | $15.10 | $1.94 |
| OPERATOR: FORKLIFT | $14.83 | $0.00 |
| OPERATOR: DRILL | $16.22 | $0.34 |
| OPERATOR: BULLDOZER | $14.00 | $0.27 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $13.93 | $0.00 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $15.60 | $0.00 |
| LABORER: ROOF TEAROFF | $11.28 | $0.00 |
| LABORER: PIPELAYER | $12.49 | $2.13 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $10.66 | $0.00 |
| LABORER: MASON TENDER - BRICK | $11.36 | $0.00 |
| LABORER: COMMON OR GENERAL | $10.66 | $0.84 |
| IRONWORKER, STRUCTURAL | $20.00 | $0.00 |
| IRONWORKER, REINFORCING | $12.27 | $0.00 |
| INSULATOR - MECHANICAL (DUCT, PIPE & MECHANICAL SYSTEM INSULATION) | $19.77 | $7.13 |
| CEMENT MASON/CONCRETE FINISHER | $14.70 | $0.00 |
| CARPENTER | $16.85 | $0.38 |
| BRICKLAYER | $18.33 | $2.50 |