Davis-Bacon
ID20260062 (Rev 2)
Coverage: Idaho • Twin Falls.
Published: May 18, 2026
Status: Active
Standard: Yes
Occupation Rates
Parsed from SAM WD content. Always validate final applicability and source text before pricing decisions.
| Occupation | Base | Fringe |
|---|---|---|
| ELECTRICIAN | $40.00 | $18.74 |
| OVER SCALE | $37.58 | $16.10 |
| OVER SCALE | $37.35 | $16.10 |
| over scale | $36.98 | $16.10 |
| ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE | $36.33 | $16.10 |
| ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE | $38.06 | $16.10 |
| IRONWORKER, STRUCTURAL | $33.37 | $22.98 |
| LABORER: GROUP 3 ASPHALT INCLUDING RAKER, SHOVELER, SPREADER, AND DISTRIBUTOR | $33.83 | $16.50 |
| LABORER: GROUP 1 FLAGGER | $33.63 | $16.50 |
| TRUCK DRIVER: WATER TRUCK | $23.89 | $9.52 |
| TRUCK DRIVER: LOWBOY TRUCK | $21.00 | $12.10 |
| TRUCK DRIVER: DUMP TRUCK | $16.19 | $0.00 |
| OPERATOR: CONCRETE BATCH PLANT | $24.94 | $11.96 |
| OPERATOR: LOADER (FRONT END) | $21.33 | $3.43 |
| OPERATOR: GRADER/BLADE | $25.17 | $9.44 |
| OPERATOR: FORKLIFT | $21.98 | $0.00 |
| OPERATOR: CRANE | $25.96 | $9.60 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $17.00 | $0.00 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $21.24 | $0.00 |
| LABORER: PIPELAYER | $14.26 | $0.00 |
| LABORER: COMMON OR GENERAL | $16.00 | $3.28 |
| IRONWORKER, REINFORCING | $27.22 | $16.70 |
| CEMENT MASON/CONCRETE FINISHER | $17.16 | $5.67 |
| CARPENTER, EXCLUDES FORM WORK | $28.00 | $0.00 |
| CARPENTER (FORM WORK ONLY) | $28.00 | $0.00 |