Davis-Bacon
MI20260097 (Rev 1)
Coverage: Michigan • Saginaw.
Published: May 18, 2026
Status: Active
Standard: Yes
Occupation Rates
Parsed from SAM WD content. Always validate final applicability and source text before pricing decisions.
| Occupation | Base | Fringe |
|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $40.00 | $23.65 |
| BOILERMAKER | $43.50 | $36.74 |
| TILE SETTER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER IS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $31.43 | $21.13 |
| TILE FINISHER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER IS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $26.24 | $21.13 |
| PLASTERER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER IS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $33.01 | $24.54 |
| BRICKLAYER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER IS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $35.14 | $24.20 |
| CARPENTER (INCLUDING ACOUSTICAL CEILING INSTALLATION & DRYWALL HANGING; EXCLUDING FORM WORK) | $35.86 | $23.69 |
| LATHER | $24.29 | $13.66 |
| ELECTRICIAN (EXCLUDING ALARM INSTALLATION) | $39.50 | $25.03 |
| ELECTRICIAN (ALARM INSTALLATION) | $30.25 | $15.00 |
| PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $31.23 | $25.25 |
| PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $33.71 | $25.25 |
| PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $39.57 | $25.25 |
| PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $41.28 | $25.25 |
| PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $43.93 | $25.25 |
| PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $47.28 | $25.25 |
| IRONWORKER: STRUCTURAL | $36.55 | $35.93 |
| IRONWORKER: REINFORCING | $36.55 | $33.37 |
| LABORER: LANDSCAPE AND IRRIGATION: GROUP 2 LANDSCAPE LABORER: SMALL POWER TOOL OPERATOR, MATERIAL MOVER, TRUCK DRIVER AND LAWN SPRINKLER INSTALLER TENDER | $27.71 | $9.10 |
| LABORER: LANDSCAPE AND IRRIGATION: GROUP 1 LANDSCAPE SPECIALIST, INCLUDING AIR, GAS AND DIESEL EQUIPMENT OPERATOR, LAWN SPRINKLER INSTALLER AND SKIDSTEER (OR EQUIVALENT) | $29.93 | $9.10 |
| LABORER: SANDBLASTER | $28.21 | $13.45 |
| LABORER: COMMON OR GENERAL; GRADE CHECKER; MASON TENDER - BRICK/CEMENT/CONCRETE; PIPELAYER | $27.68 | $13.45 |
| PAINTER: DRYWALL FINISHING/TAPING | $30.22 | $22.22 |
| PAINTER: BRUSH AND SPRAY | $29.23 | $19.11 |
| CEMENT MASON/CONCRETE FINISHER | $25.47 | $12.38 |
| PLUMBER, EXCLUDES HVAC PIPE AND UNIT INSTALLATION | $46.00 | $22.99 |
| PIPEFITTER, INCLUDES HVAC PIPE AND UNIT INSTALLATION | $46.00 | $22.99 |
| ROOFER | $30.38 | $19.87 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $41.34 | $27.39 |
| SHEET METAL WORKER (INCLUDING HVAC DUCT INSTALLATION; EXCLUDING HVAC SYSTEM INSTALLATION) | $26.83 | $23.78 |
| TRUCK DRIVER: TRACTOR HAUL TRUCK | $13.57 | $1.18 |
| TRUCK DRIVER, INCLUDES DUMP AND TANDEM TRUCK | $12.00 | $0.00 |
| PAINTER: ROLLER | $22.02 | $6.02 |
| OPERATOR: LOADER | $17.62 | $0.00 |
| OPERATOR: TRACTOR | $19.10 | $8.48 |
| OPERATOR: BULLDOZER | $17.50 | $8.67 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $18.31 | $13.84 |
| IRONWORKER, ORNAMENTAL | $18.48 | $7.93 |
| FLOOR LAYER: VINYL FLOORING | $16.81 | $3.73 |
| CARPENTER (FORM WORK ONLY) | $16.50 | $1.65 |