Davis-Bacon
NJ20260064 (Rev 1)
Coverage: New Jersey • Sussex.
Published: May 18, 2026
Status: Active
Standard: Yes
Occupation Rates
Parsed from SAM WD content. Always validate final applicability and source text before pricing decisions.
| Occupation | Base | Fringe |
|---|---|---|
| CEMENT MASON | $49.60 | $37.96 |
| IXER, MULCHING, STRINGING, SEEDING, FERTILIZING, POLE, SPREAD BITUMINOUS DISTRIBUTOR, WATER PULL (ENTIRE UNIT), TRACTOR TRAILER, REEL TRAILER, AND SIMILAR TYPES OF VEHICLE GROUP 4: WINCH TRAILER DRIVER | $57.42 | $34.02 |
| PER HOUR ADDITIONAL FOR EACH ADDITIONAL FIFTY FEET THEREAFTER | $57.42 | $34.02 |
| IXER, MULCHING, STRINGING, SEEDING, FERTILIZING, POLE, SPREAD BITUMINOUS DISTRIBUTOR, WATER PULL (ENTIRE UNIT), TRACTOR TRAILER, REEL TRAILER, AND SIMILAR TYPES OF VEHICLE GROUP 4: WINCH TRAILER DRIVER | $58.84 | $35.06 |
| TIMES THE JOURNEYMAN RATE | $65.43 | $42.86 |
| TIMES THE JOURNEYMAN RATE | $71.97 | $46.42 |
| PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $52.88 | $37.50 |
| PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $56.59 | $37.50 |
| PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $58.22 | $37.50 |
| PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $60.13 | $37.50 |
| PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $61.72 | $37.50 |
| ONE DAY OF THE CALENDAR WEEK DURING WHICH THE HOLIDAY OCCURS | $52.24 | $50.32 |
| WORKER WORKS THREE DAYS FOR THE SAME EMPLOYER WITHIN A PERIOD OF TEN WORKING DAYS CONSISTING OF FIVE WORKING DAYS BEFORE AND FIVE WORKING DAYS AFTER THE DAY UPON WHICH THE HOLIDAY FALLS OR IS OBSERVED | $51.65 | $38.53 |
| WORKER WORKS THREE DAYS FOR THE SAME EMPLOYER WITHIN A PERIOD OF TEN WORKING DAYS CONSISTING OF FIVE WORKING DAYS BEFORE AND FIVE WORKING DAYS AFTER THE DAY UPON WHICH THE HOLIDAY FALLS OR IS OBSERVED | $50.95 | $38.53 |
| PAINTERS: (WORK ON BRIDGES (MAJOR BRIDGES DESIGNED FOR COMMERCIAL NAVIGATION)) | $58.28 | $33.85 |
| PAINTERS:: BRUSH AND ROLLER (REPAINT WORK, ON PROJECTS ON WHICH NO MAJOR ALTERATIONS OCCUR.) | $29.05 | $18.91 |
| PAINTERS:: BRUSH AND ROLLER (NEW CONSTRUCTION) | $40.19 | $22.72 |
| PIPEFITTER | $57.97 | $40.22 |
| ONE DAY OF THE CALENDAR WEEK DURING WHICH THE HOLIDAY OCCURS | $46.51 | $31.82 |
| PLUMBER: EXCLUDING HVAC PIPE INSTALLATION (MIDDLESEX COUNTY (DOES NOT INCLUDE THE BOROUGHS OF DUNELLEN AND MIDDLESEX; BOROUGH OF SOUTH PLAINFIELD)) | $46.41 | $31.82 |