Davis-Bacon
NY20260101 (Rev 0)
Coverage: New York • Cayuga.
Published: Jan 02, 2026
Status: Active
Standard: Yes
Occupation Rates
Parsed from SAM WD content. Always validate final applicability and source text before pricing decisions.
| Occupation | Base | Fringe |
|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR (MECHANICAL (Duct, Pipe & Mechanical System Insulation)) | $43.25 | $27.29 |
| BRICKLAYER BRICKLAYERS, STONEMASONS, CEMENT MASONS, PLASTERERS, POINTER, CLEANERS & CAULKERS | $38.30 | $23.71 |
| MARBLE, TILE AND TERRAZZO FINISHERS | $26.46 | $19.64 |
| MARBLE, TILE, AND TERRAZZO WORKERS | $34.92 | $21.29 |
| TILE SETTER | $30.69 | $20.91 |
| CARPENTER (Excludes Drywall Hanging, Form Work and Metal Stud Installation) | $32.64 | $21.97 |
| SOFT FLOOR LAYER (Hardwood Floors) | $28.90 | $21.63 |
| CARPENTER Drywall Hanging Only | $43.50 | $30.22 |
| Form Work Only | $43.50 | $30.22 |
| INSTALLER - METAL STUD | $44.72 | $31.23 |
| ELECTRICIAN (Includes Low Voltage Wiring) | $45.00 | $31.12 |
| ELEVATOR MECHANIC | $57.73 | $38.43 |
| POWER EQUIPMENT OPERATOR: Backhoe/Excavator/Trackhoe | $60.13 | $37.50 |
| Crane | $61.72 | $37.50 |
| IRONWORKER, ORNAMENTAL | $35.49 | $32.30 |
| IRONWORKER, REINFORCING | $42.63 | $53.70 |
| IRONWORKER, STRUCTURAL | $42.63 | $53.70 |
| LABORER Common or General | $29.57 | $22.90 |
| Mason Tender - Cement/Concrete | $25.67 | $20.90 |
| PAINTER (Spray) | $28.35 | $25.21 |
| GLAZIER | $27.90 | $27.50 |
| PIPEFITTER | $37.47 | $27.40 |
| ROOFER | $50.25 | $39.62 |
| OPERATOR: Forklift | $38.46 | $28.52 |
| PLUMBER | $37.19 | $27.89 |
| OPERATOR: Bobcat/Skid Steer/Skid Loader | $41.10 | $19.26 |
| PAINTER (Brush and Roller) | $25.37 | $19.91 |